  Colored stone metal tileEaves and ridge tile installation instructions.

The metal tile should be prepared in advance with certain installation techniques before installation.

1, first carefully read the metal tile project construction node detailed design scheme, grasp the layout diagram, network node structure and construction organization scheme provisions.

2. The metal tile construction team of the organization shall learn and train the above specific contents, and the professional and technical personnel shall interpret the construction standards and requirements to the workers.

3, the preparation of colored stone metal tile project construction actual operation regulations, issued the completion date and safe use requirements.

4. Prepare the detailed materials of the metal tile project construction node issued in advance.

5. Check whether the structural assembly of colored stone metal tile before installation meets the assembly standard of row structure.

These are things that need to be paid attention to before installation. Many colleagues who configure commodities also provide professional services for the whole installation process of some projects, but many of them have to do it by themselves. Therefore, they have to master the matters needing attention in assembly in advance, ensure their own safety and give themselves a smooth installation process.

Preparation before 1. construction

1) Bottom layer: colored stone metal tile cocoa with bottom layer for all materials above the flat roof.

2) Wood keel ceiling shall be dried wood (metal composite material) with a specification of 30mm × 25mm, and the surface shall be treated with anticorrosion.

3) Special tools are prepared in advance: hammer head, meter ruler, ink bucket wire, electric hand drill, aluminum cutting machine and bending machine.

4) Auxiliary materials: sealant, riveting and steel nails.

Bottom layer requirements and solutions for 2. roof waterproofing

1. During construction, the moisture-proof bottom layer should be basically dried, with a water content of less than 9% appropriate. During construction, the moisture-proof bottom layer should be dry and manic, with a water content of less than 9% appropriate. The simple determination method is to cover a rubber pad with an area of about 1 square meter and a thickness of 1.5-2.0mm on the surface of the bottom layer and place it for 2-3 hours. If there is no watermark on the surface of the covered bottom layer, there is no watermark, construction standards can be met.

2. Before construction, first use gray knife and broom to remove the dirt such as protrusions and small bumps in cement mortar on the bottom surface, and completely clean the dust and dirt. The corner line, pipeline root, deodorant floor drain and outlet should be carefully removed. If oil stains and rust are found, steel brush, sandpaper and organic solution should be used to make them clear and tidy. 3, moisture-proof bottom layer according to the design points with 1:3 mixed mortar plastered into 1/50 roof drainage inclination, the surface to be scraped flat plastered, can not have uneven, loose and sand off ash and other problems. Outlet or deodorant floor drain parts should be less than all the ground waterproof, easy to remove water. The pipe part with waterproof casing should be about 20mm higher than the bottom surface. The corner line part should be made into a small fillet of about 10mm in half to facilitate the construction of the wiping project.

3, all pipes, sanitary facilities, deodorant floor drain or water outlet must be assembled firmly, the joints are tight, the closing is round, and there is no loose condition.


Keywords: Colored stone metal tile